Cost and Project
Project Cost Management
- It is the knowledge area that consists of processes involved in planning, estimating, budgeting, financing, funding, managing and controlling costs so as to complete the project within budget.
Cost Estimation; Types of Cost Estimate
Estimate Cost
Input | Tools and techniques | Output |
---|---|---|
|
|
|
Importance of cost estimation
- It provides standard that can be used to compare and control the expenditures during the course of the project.
- It helps the project manager to allocate scarce resources as the project progresses.
Classification of Project Cost
1. Direct vs Indirect Cost
- Direct cost is the cost that can be charged against the project. Eg: cost of manpower and materials used.
- Indirect cost is the cost indirectly involved in the project. Eg: overhead cost, selling and administrative cost.
2. Recurring and Non-recurring Cost
- Recurring cost is the cost that are repeatedly incurred throughout the project lie cycle.
- Non recurring cost is the one time cost that are incurred at the beginning or at the end of the project.
3. Fixed vs Variable Cost
- Fixed cost is the cost that do not vary with usage. Eg: Cost incurred in purchase of capital equipment
- Variable cost is the cost that vary directly with the usage. Eg: labor cost.
4. Normal vs Expedited Cost
- Normal cost is the cost incurred when project tasks are completed according to the original planned duration.
- Expedited cost is the crash cost which are unplanned incurred as a result of steps taken to accelerate project completion.
Cost Estimating Methods
1. Ballpark estimate
- It is done when there is no sufficient information or time available.
- It helps in rough estimate of resources needed for a project in initial phase.
- It should attempt to have 30% accuracy.
2. Feasibility estimate
- It is done after preliminary work is completed.
- It is generally performed when information on material cost is available.
- It should attempt to have 10% accuracy.
3. Definitive estimate
- It is done after completion of design work.
- It requires clear understanding of scope and capabilities of the project.
- It attempts to have 5% error margin.
4. Comparative estimate
- It uses historical data of previous project as a reference for estimating cost of current project.
5. Parametric estimating
- It uses mathematical model for estimation.
6. Vendor bid analysis
- It estimates using bids and allowances for gaps in bid slope.
7.Reserve analysis
- It adds contingency to each activity cost estimate as zero duration item.
Cost Budgeting; Cost Aggregation; Deriving Budget from Activity Cost
Determine Budget
- Budgeting is the process of plannin. for the cost of project resources.
- Budget implies the level of management support.
- Budget is estimated as:
Materials + Labor + Equipment + Capital + Overhead + Profit = Bid
Input | Tools and techniques | Output |
---|---|---|
|
|
|
Types of Budgeting
1. Top - down
- Top managers estimate overall budget for the project.
- The estimates are broken down at each lower level.
2. Bottom - up
- Low level managers estimate budget for each work package.
- Overhead and profits are added to develop project budget.
3. Negotiated
- It is the combination of top down and bottom up budgeting.
- Both are prepared and compared.
- Any differences are negotiated.
4. Activity based costing
- Assign cost to activities that uses resources.
- Identify cost drivers associated with activity.
- Compute cost rate per cost deliver unit.
- Multiply cost drive rate times the volume of cost driver units used by the project.
Budget Contingency
- It is the allocation of extra funds to cover uncertainties.
- It provides protection against unknown and uncertain elements.
Cost Control Process; Cost Control Methods
Control Costs
Input | Tools and techniques | Output |
---|---|---|
|
|
|
EV Management and Benefits; Variance Analysis
Earned Value Management (EVM)
- EVM is a project management technique for measuring project performance and progress in an objective manner.
- It helps to find variances in projects based on comparison of work performed and work planned.
- It is used on cost and schedule control.
Equations
Assumptions:
1. Planned value (PV) = budgeted cost
2. Earned value (EV) = actual work completed
3. Actual cost (AC) = cost incurred
4. Estimate to complete (ETC) = what is left
5. Estimate at completion (EAC) = what final cost will be
Analysis:
1. Cost variance (CV) = EV - AC
- Negative = under budget
- Positive over budget
2. Schedule variance (SV) = EV - PV
- Negative = behind schedule
- Positive = ahead of schedule
3. Cost Performance Index (CPI) = EV / AC
- How much we get for every dollar we spend?
4. Schedule Performance Index (SPI) = EV / PV
- Progress as % against plan
5. ETC = EAC - AC
- How much more we have to spend?
6. Variance at completion (VAC) = BAC - EAC
7. EAC = BAC / CPI
Q) If EV is twice its AC of the project, calculate CPI and CV. Is the project over or under budget?
Let AC = x, then: EV = 2x
Now,
CPI = EV / AC = 2x / x = 2
Also,
CV(%) = (EV - AC) / AC * 100%
= (2x - x) / x * 100%
= 100%
As, EV-AC is positive, the project is under budget.
Q) If SPI is 0.75 with earned value being 60. Calculate planned value and also state whether the project is ahead or behind schedule?
Given: SPI = 0.75 EV = 60
We know that,
SPI = EV / PV
or, PV = 60 / 0.75
or, PV = 80
Now,
Schedule variance (SV) = EV - PV = 60 - 80 = -20
As, SV is negative, the project is behind schedule.
Q) A project is scheduled for time of 12 months with estimated cost of 400000. After 3 months, evaluation is done and identified that 40% of work is accomplished with cost of 200000. Calculate cost and schedule variance for the project.
Given: Planned schedule = 12 months Estimated cost = 400000 Planned value = Estimated cost = 400000
At the end of 3 months:
PV = 400000/12 *3 = 100000
Project completed = 40%
EV = 40% of 400000 = 160000
AC = Cost incurred = 200000
Now,
Cost variance (CV) = EV - AC = 160000 - 200000 = - 40000
As, CV is negative, the project is over budget.
Schedule variance (SV) = EV - PV = 160000 - 100000 = 60000
As, SV is positive, the project is ahead of schedule.
Ⓒ Copyright ESign Technology 2019. A Product of ESign Technology. All Rights Reserved.